Status of NE-CAT Sector 24 ActivitiesMarch 2008
The month of March and the entire 2008-1 APS run cycle have been a very productive period for NE- CAT users. Both undulator beamlines are heavily booked and operating very reliably- with no significant down times due to beamline malfunctions. We now project that both beamlines will end 2008-1 with utilization factors of greater than 80%.
Microdiffraction The acquisition of the MD2 microdiffractometer on 24-ID-E has proved to be a major success, providing new opportunities for users, particularly with very small crystals. The MD2 has been such a success that we are acquiring another MD2 microdiffractometer for the other undulator beamline 24-ID-C. The new MD2 will be identical to the present MD2 but will have a Kappa installed. The providers, ACCEL/Maatel, have provided us with an estimated delivery date of October 2008.
New Crystal Illumination System The advent of the MD2 has caused us a problem. Before users had experience with the sample imaging system of the MD2, NE- CAT users praised the crystal visualization system of the system in use for several years at 24-ID-C. However, now viewing the MD2 visualization system, more and more users are recommending a similar quality system be installed for 24-ID-C. Prior to delivery of the second MD2, which would address this recommendation, we have installed and are testing a new crystal illumination system for 24-ID-C. The new illumination system consists of a LED light source combined with an opal diffuser, backlighting the sample and in line with the long-distance microscope. Early user experience with this new illumination system is very positive, with the crystals more easily seen.
Sample Placement Robotics System Modifications to the ALS sample placement robotic system have now been finished and use of the robot is being made available to users. Some of the modifications made included elimination of the few remaining sources of icing and installation of a gravity feed liquid nitrogen filling system for the sample Dewar. The first user group to use the robot reported that during the course of their experiments involving the mounting and dismounting of more than 100 crystals only one crystal did not mount correctly. The source of this problem is known and will be eliminated. A photograph of the sample placement robotics system is shown below.
NE- CAT Organized Workshop NE- CAT is organizing a workshop in conjunction with the APS User Week 2008. Workshop WK04 titled “Software for Challenging Cases in Macromolecular Crystallography” will be chaired by Igor Kourinov and Frank Murphy of our staff and will be held all day on Tuesday, May 6, 2008. The agenda is posed on: http://www.aps.anl.gov/Users/Meeting/2008/Workshops/wk04_MXsoftware.php
|
Recent Highlights10/07/2009 *NE-CAT's executive committee member Thomas Steitz shares 2009 Nobel Prize in Chemistry* The Nobel Assembly at the Karolinska Institute in Sweden announced today that Thomas Steitz is one of three winners of the 2009 Nobel Prize in Chemistry for his work describing the structure and function of the ribosome. Thomas Steitz is a member of NE-CAT's executive committee and a frequent user of NE-CAT beamlines. 09/03/2009
Crystal Structure of the ATP-Gated P2X4 Ion Channel in the Closed State, Toshimitsu Kawate, Jennifer Carlisle Michel, William T. Birdsong, and Eric Gouaux, Nature 460, 592-598 (2009) Formation of the First Peptide Bond: the Structure of EF-P Bound to the 70S Ribosome, Gregor Blaha, Robin E. Stanley, and Thomas A. Steitz, Science 325, 966-970 (2009) Structures of the Ribosome in the Intermediate States of Ratcheting, Wen Zhang, Jack A. Dunkle and Jamie H.D. Cate, Science 325, 1014-1017 (2009) 09/02/2009 August 2009 status report now available. 08/06/2009 July 2009 status report now available. 06/30/2009 June 2009 status report now available. 06/18/2009 Looking for Ways to Improve Vaccines Against the Deadly Rotavirus 06/09/2009 May 2009 status report now available. 05/01/2009 April 2009 status report now available. 03/06/2009 February 2009 status report now available. 02/16/2009 New MD2 installed on 24-ID-C beamline with sample placement robot now available to users. 02/09/2009 January 2009 status report now available. 1/23/2009 NE-CAT Resource Advisory Committee Meets. See pic. 1/13/2009 December 2008 Status report available. 12/11/2008 November 2008 Status report available. 11/04/2008 Featured Publication Structure of a complex of the ATPase Sec A and the protein-translocation channel J. Zimmer, Y. Nam & T. Rapoport Nature 455, 936-945 (2008) Click here for full article. NE-CAT’s second MD2 microdiffractometer is delivered. |
|